Town of Parry Sound staff are laying the groundwork to eventually replace Sewage Pumping Station 11 on Meadow Street, which services the south end of town.
According to Mike Kearns, the town’s director of public works, the station has been operating near full capacity for some time and there is proposed development pressures that will require a larger capacity than is currently available.
At Kearns request, council approved a pre-budget expenditure of up to $284,000 at a meeting on Oct. 21, to begin the engineering design work to replace the sewage pumping station.
Kearns said the goal is to have designs shovel ready and have the Town in a position to act quickly should any provincial or federal grants come available.
This summer the Town began construction to replace the Champagne Street sanitary pumping station. That $20 million project was made possible due to a $13.1 million dollar grant from the province.