Struggles with CN Rail continue for the Forest Street project

The Forest Street project continues, but still without approval from CN Rail.  At this week’s meeting, Director of Public Works Peter Brown told council that the contractors have completed all they can up to the track and have move past them.

Brown told council at their regular meeting on Tuesday that a 50-page application to CN Rail is complete.

He says a big hurdle with the project at the crossing is the cost.

It’s hoped that CN Rail will approve the application and work can be done at the crossing soon as this project has a deadline of the end of this year in order to get the funding from the government.

Continue Reading

cklp Now playing play

- Advertisement -

Related Articles

- Advertisement -

Latest News

Parry Sound Salvation Army radiothon returns Dec. 4

We will be on-air from 6 a.m. to 6 p.m. on Dec. 4 raising awareness and funds for the local charitable organization.

Santa Claus is coming to Parry Sound Nov. 28

The annual Santa Claus parade will take place downtown Parry Sound at 4 p.m. on Saturday, Nov. 28.

Hydro One releases route alternatives for Sudbury-Barrie transmission line

A series of route alternatives for the Sudbury to Barrie transmission line were made public on Nov. 9.

One-of-a-Kind Christmas artisan market returns to Parry Sound Nov. 27, 28

The event, which runs 2-7 p.m. on Friday, will feature more than 40 local vendors.

Parry Sound District EMS’s annual ‘Fill an Ambulance’ Toy Drive to run Nov. 26, 27, 28

The three-day initiative, will run Thursday and Friday from 9 a.m. to 5 p.m. and Saturday from 9 a.m. to 1 p.m. outside the local Walmart and Canadian Tire.
- Advertisement -