The municipality of Whitestone is holding firm on its decision to withhold a $250,000 one-time payment to the West Parry Sound Recreation and Cultural Centre until the project board meets the municipalities requirements.
At a meeting on December 10, council passed a motion reiterating its stance from April – that the financial assistance the municipality agreed to provide is conditional on a review of the project’s operating model, projected operating revenue, costs and reserve requirements for the facility be conducted by an independent consultant.
Although the project board provided a financial report conducted by BDO Canada, council wasn’t and still isn’t satisfied.
“I am not in favour of sending them the money until they do the report that we all agreed should have been done,” said Coun. Brian Woods. “They didn’t fill the conditions that we imposed as a council.”
With a 3-1 vote, council reiterated their stance to withhold funding. Mayor George Comrie voted against the motion, and Coun. Janice Bray abstained.
Coun. Joe Lamb also reiterated his concerns with the known financials associated with the project.
“We did not believe in the financials and the numbers that were being put forward (in April) and frankly I do not believe in them today. We wanted transparency and full disclosure to the taxpayers of West Parry Sound – something I still find lacking,” he said.
The project, which was projected to cost $36.3 million is now estimated to cost $39.6 million.