‘Unforseen site conditions’ are causing the West Parry Sound Recreation and Cultural Centre board to dip into the contingency budget.
According to project manager Andy Gordon, who provided an update to the Board on June 12, early site work has cost $1.14 million more than projected.
He says, in early May, when work first began at 44 Joseph Street, soil contaminated with heavy metal was found at the back of the site. Its removal cost $325,000 more than projected, while replacement fill has cost $420,000 more than anticipated.
A report shows bedrock blasting is also nearly $400,000 overbudget.
At Gordon’s recommendation, $500,000 from the contingency fund, roughly 30 per cent, will be used to help offset the overage.
“I’ve spoken to the construction manager, and we believe that is an appropriate level to spend because early works is where we get the majority of the risk on the project,” said Gordon.
He said they will look for savings in other aspects of the project to try and recoup the remaining $614,000 in overages and get the budget back in line.
Early site work is expected to be completed in August, at which point construction of the physical building will begin.