The Federal Government’s Department of Fisheries and Oceans (DFO) has committed to spending $196,000 to address priority repairs at the Parry Sound town dock.
“The Town Dock is a focal point of Parry Sound’s harbour and attracts thousands of visitors to the area each year,” said Parry Sound Mayor Jamie McGarvey. “We have a good working relationship with DFO and look forward to working with them to complete the immediate repairs and create a path forward to ensure the integrity of the dock moving forward.”
A condition assessment, conducted early last year, outlined four priority levels of repairs needed. A report outlining the work needed over the next 15 years was released on April 15.
Town officials say the top priority needs involve addressing safety issues for all dock users. This includes fixing up cracks in the concrete that could be trip hazards, stairs, railings and more.
Priority 2 repairs, which the report suggests should be completed within one to five years, total approximately $625,000. Priority 3 repairs, which should be completed within six to 10 years, total $520,000, and Priority 4 repairs, which should be completed within 11 to 15 years, total $6.7 million.
Parry Sound CAO Clayton Harris says conversations are being had around finding the $625,000 needed to complete priority 2 repairs, which includes addressing various deficiencies in the concrete and repairing bollards.