The Tamarack North Centre, which houses Parry Sound’s new six-lane pool, will be opening Oct. 10.
That’s according to local YMCA officials, who confidently announced the opening date in an email blast on Aug. 10.
During a board meeting on Aug. 13, Ball Construction Vice President Rod Aitken provided an update on construction.
According to Aitken, the gymnasium is complete, and the gym area and multi-purpose rooms are also complete. He says the focus over the course of the next month will be on finishing up the pool area. Drywall, acoustic paneling, and tile was recently installed in the pool area, and lockers and toilet partitions installed in the changerooms.
The project is expected to be substantially complete by mid-September.
According to the YMCA, membership will go on sale Sept. 1.
The latest update to the project board can be found at wpspoolandrec.ca